Municipality Dobberkau

New construction of a municipal wastewater treatment plant for 50 PE

 

Profile:

System: klärocom Location, building owner:
WVSO Wasserverband
Standal - Osterburg
D-39576 Wittenmoor/Stendal

Designer / consultant::
utp umwelttechnik GmbH
Weidenberger Str. 2-4
D-95517 Seybothenreuth

Installation company:
utp service GmbH
Weidenberger Str. 2-4
D-95517 Seybothenreuth

Filtration level:

  • COD --> 90mg/l
  • BOD5 --> 20mg/l
  • NH4-N-->10mg/l
  • Ninorg.-->25mg/l
  • SS-->50mg/l

Air blower type: Becker side-channel blower

Structural engineering: Monolithic cylindrical tank

Commissioning date: May 2022

Dimensioning:

PE

Scope of services of utp umwelttechnik GmbH

Ready-to-use overall performance consisting of:

  • detailed engineering and construction site management
  • civil works and installation
  • asphalt works
  • fence building works
  • manufacturing, delivery and assembly of the tanks technology as well as of technical equipment
  • control unit / automation technology
  • EMSR-technology and telecontrol engineering

Specifics

  • high groundwater level
  • on-site control devices via touch panel
  • Effluent pump station for clarified water
  • remote monitoring by telemetry modul
  • Total construction time: 1.5 weeks